MANILA, Philippines – Around 1,105 million liters of water every day goes down the drain due to leaks or illegal connections, Maynilad Water Services, Incorporated said on Wednesday, May 17.
This loss is 40% of the 2,695 million liters of water allocated to Maynilad from the Angat Dam.
During a hearing Wednesday of the House committee on Metro Manila development on the alleged water depletion in the National Capital Region, Manila Representative Rolando Valeriano expressed alarm over the amount of wastage, saying that “this is not a joke.”
The previous amount of water loss was even higher before DMCI-MPIC Water Company took over the water concession, Maynilad chief operating officer Randolph Estrellado said.
Old water pipes
He noted that from 1997 until 2006 the previous owner hardly did any repairs to the pipelines.
He said that 75% of the pipes they inherited in 2006 were replaced which caused a significant reduction in water loss. This upgrade caused them P21.7 billion.
While he recognized the reduction in the amount of wasted water, Maynilad’s chief said that a huge amount was still being wasted.
“Yung dating 68% na non-revenue water naibaba na namin siya to 40%, pero ho ang nawawala pa rin is mataas pa rin pero malaki pa rin yung nabawas na,” he said.
(We have already reduced the previous 68% non-revenue water to 40%. However, there is still a significant remaining portion that needs to be addressed, although a substantial reduction has already been achieved.)
Processing of permits impedes immediate repair
One of the challenges hounding water concessionaires in repairing leaks is the tedious process of securing permits from local governments, Estrellado said.
Visible leaks can be addressed immediately as acquiring a permit is swifter, however, leaks that are not visible in the street take them a while to repair, he said.
“It takes us 60 days before we can acquire a permit from the LGU,” Estrellado said.
“At the moment, we have around 21 locations where our permits to repair leaks are still pending. That is the issue we are currently facing,” he said. – Rappler.com