Phase 2 of Boracay road rehabilitation underway

Apr 20, 2019 - 11:21 PM

Illegal structures affected by Phase 2 of the road construction will be removed prior to full road rehabilitation, says the Boracay Inter-Agency Rehabilitation Management Group

ROAD WORKS. The second phase of the Boracay road rehabilitation has begun. Photo by Boy Ryan Zabal/Rappler

Boracay main road rehab 97% complete

Dec 03, 2018 - 10:41 PM

The DPWH says Boracay's main road, a 4.1-km stretch, is nearly complete but the rest of the 20-km circumferential road will take another year

ROAD TO RECOVERY. Boracay may be open, but the rehab continues. Photo by Adrian Portugal/Rappler

DPWH: Boracay Circumferential Road to fully open by December 2018

Oct 20, 2018 - 6:18 PM

When Boracay reopens on October 26, one lane along the 2.66-kilometer road from Cagban Port to Hue Hotel will already be passable

UNDER CONSTRUCTION. Inside roads in Boracay Island is still under construction, days away from the reopening. Photo from Net Sacapano

LOOK: Boracay to open with war zone-like roads?

Aug 20, 2018 - 5:50 PM

'The island definitely looks like a war zone with muddy and empty roads. We hardly see contractors on the main road,' says Boracay Foundation, Inc.

MUDDY. Boracay residents question the optimism of government officials that the island will be ready for opening on October 26. Photos by Bong Arban and Jack Jarilla. Photo from Boracay Foundation, Inc.


Local DPWH officials await authority to implement Boracay road rehab project

Jun 13, 2018 - 10:25 AM

The road widening is a top priority project of the Boracay inter-agency task force

DBM to release P490M for Boracay roads

May 02, 2018 - 10:20 AM

Budget Secretary Benjamin Diokno also says P448 million was released to the Department of Labor and Employment for assistance to Boracay workers and residents